All-sky Release - PSC - Photometric Sensitivity
The Level 1 Specifications call for a 10-sigma detection (0.109 mag) at the
following magnitude levels: J = 15.8, H = 15.1, and Ks = 14.3 for
unconfused sources outside of the Galactic Plane (|b| > 10 deg).
The 2MASS observing strategy required the observation of a 1-degree
long calibration tile several times during a night of observation.
The calibration session involved 6 repeated observations of the
calibration tile and thus 6 observations of each star within
the tile. These repeated observations give a direct measure
of the instantaneous sensitivity of the system. The plot
at right shows the results of one of these calibration sessions.
Each point in the plot is the RMS of one
of the stars in the calibration field as a function of the
star's magnitude. The green bars are the ensemble statistics
for each half-magnitude bin. The point at which the ensemble statistics
cross the 10-sigma line marks the sensitivity of that particular
calibration set.
Since each of these calibration sessions
sample the survey sensitivity as a function of other
survey variables -- particularly background and seeing --
the ensemble of calibration observations permits 2MASS to
map its real-time sensitivity to the instantaneous background
and seeing. (This link points to a document
which describes this process in excruciating detail).
Background and seeing values are extracted for each of the 2MASS
science tiles, directly measuring their limiting sensitivity on a
tile-by-tile basis. The plot at right shows
a nightly summary of the sensitivity of both the science and
calibration data for the same random night of 2MASS data. The
horizontal lines in the plot are thresholds for scoring data based on
the knowledge of sensitivity variation from the calibration history of
the project as described in the paragraph above.
Points falling below the middle horizontal dashed line exceed the
survey's sensitivity targets (Several lines appear because the
data can receive a range of sensitivity scores to aid in
assigning priority for re-observation. The lines are off of the top of the
J-band plot -- J-band consistently exceeds the survey's sensitivity
requirement). The 2MASS Quality Assurance review process permitted
the rescheduling of tiles with sub-threshold sensitivity in any
one of the bands. The histogram of achieved
sensitivity for the tiles selected for final release indicates that
the sensitivity requirement was met for virtually all tiles in all
bands, with a small number of exceptions lacking 0.1-0.2 mag in sensitivity.
Applying the estimation of instantaneous sensitivity to each tile yields
a complete 2MASS sky map of the variation of sensitivity in each waveband.
The 2MASS all-sky release dataset meets the Survey sensitivity requirements
because the sensitivity of each tile was determined shortly
after the time of observation as part of routine Quality Assurance
and poor-sensitivity tiles were reobserved
until they could be replaced with data that met the specifications.
The above statement would be rigorously true were it not for
the fact that a small number of tiles either could not be re-observed
or had poor sensitivity in every re-observation (as reflected in the
small extensions of the histograms above to sensitivity levels just
below the Level1 threshold).
|